Dilovası Power Plant
Client : Ortadoğu Enerji
Installed Power : 2,1 MWe
October 2015 Commissioning Date :

The work done

Total Capacity: 2,126 MW (2 Gas Engines) Biogaz Power Plant Mechanical Installation Works

-Main Gas Line Piping
-Flare Gas Combustion Chimney Installation works
-Gas Cooling System ( Chiller ) Installation
-Gas Engine installations and installations

The work done:

Gas engine assembly

Gas engine jacket water chiller design, manufacture and installation

Gas engine oil line design, manufacture and installation

Gas engine exhaust flue line design, manufacture and installation

Gas line piping design, fabrication and installation

Cooling water system design, manufacture and installation

Clean and dirty oil tank design, manufacturing, design and assembly

Clean and dirty oil tank design, manufacturing, design and assembly

Dilovası Power Plant